
Heavy rainfall caused significant erosion on Lawrence Hargrave Drive at Coalcliff in 2024. Work has now been completed to repair this section of the critical road. Photo: Transport for NSW.
Two years after record-breaking rainfall led to landslips along Lawrence Hargrave Drive at Coalcliff, repair work has been completed.
The rain had caused the slope above Stony Creek, just south of Bombora Way, to erode and slip away.
Transport for NSW installed temporary measures to prevent further erosion, including an asphalt edge and a pipe to redirect water away from the damaged slope.
Permanent repair work began in late April and involved clearing vegetation and loose soil, rebuilding sections of the embankment, placing rock to stabilise the slope and installing a new concrete footing to support the guardrail.
Repair crews were forced to use abseiling ropes in some sections to remove loose material by hand, while specialised excavators were called in to work around the pedestrian bridge above the site.
The $835,000 project was jointly funded by the Federal and NSW governments under the Disaster Recovery Funding Arrangements.
NSW Roads Minister Jenny Aitchison said Lawrence Hargrave Drive was a critical connection for communities across the northern Illawarra.
“This $835,000 investment has delivered permanent repairs to stabilise the slope and improve the resilience of Lawrence Hargrave Drive,” she said.
“Crews have worked in challenging conditions to rebuild the embankment, stabilise the slope and install new infrastructure to support the guardrail.”
The project forms part of more than $25 million provided by the two governments since 2022 to repair landslip damage along Lawrence Hargrave Drive.
Fifteen landslip sites along the corridor have now been repaired, with investigations and procurement progressing for the five remaining sites.
Further work is expected to begin in early 2027 near the new Coalcliff pedestrian bridge, including drainage repairs.
Additional work across the broader corridor has included installing geotechnical monitoring equipment to track slope movement and groundwater levels, investigating drainage systems to inform future upgrades and carrying out progressive slope stabilisation at nearby sites.
Federal Member for Cunningham Alison Byrnes said everyone who used the road understood how important it was as a connecting road for the northern Illawarra suburbs, both to Wollongong and Sydney.
“When the road is disconnected, it has a profound impact on our day-to-day lives,” she said.
“I know that local people also understand the complex challenges facing repairs along this stretch, and I want to thank everyone in the community for your patience while these works were underway.
“The concurrent spate of natural disaster events has severely impacted stability along this vulnerable stretch of road, and while I understand some further works along Lawrence Hargrave Drive are still awaiting repair, I am pleased to see this section completed.”











