16 June 2026

15 sites repaired, 5 to go: The complex challenge of fixing weather-beaten Lawrence Hargrave Drive

| By Jen White
Start the conversation
Erosion on road

Heavy rainfall caused significant erosion on Lawrence Hargrave Drive at Coalcliff in 2024. Work has now been completed to repair this section of the critical road. Photo: Transport for NSW.

Two years after record-breaking rainfall led to landslips along Lawrence Hargrave Drive at Coalcliff, repair work has been completed.

The rain had caused the slope above Stony Creek, just south of Bombora Way, to erode and slip away.

Transport for NSW installed temporary measures to prevent further erosion, including an asphalt edge and a pipe to redirect water away from the damaged slope.

Permanent repair work began in late April and involved clearing vegetation and loose soil, rebuilding sections of the embankment, placing rock to stabilise the slope and installing a new concrete footing to support the guardrail.

Repair crews were forced to use abseiling ropes in some sections to remove loose material by hand, while specialised excavators were called in to work around the pedestrian bridge above the site.

The $835,000 project was jointly funded by the Federal and NSW governments under the Disaster Recovery Funding Arrangements.

READ ALSO Motorists warned of delays due to landslip repairs on Lawrence Hargrave Drive at Coalcliff

NSW Roads Minister Jenny Aitchison said Lawrence Hargrave Drive was a critical connection for communities across the northern Illawarra.

“This $835,000 investment has delivered permanent repairs to stabilise the slope and improve the resilience of Lawrence Hargrave Drive,” she said.

“Crews have worked in challenging conditions to rebuild the embankment, stabilise the slope and install new infrastructure to support the guardrail.”

The project forms part of more than $25 million provided by the two governments since 2022 to repair landslip damage along Lawrence Hargrave Drive.

Fifteen landslip sites along the corridor have now been repaired, with investigations and procurement progressing for the five remaining sites.

Further work is expected to begin in early 2027 near the new Coalcliff pedestrian bridge, including drainage repairs.

Additional work across the broader corridor has included installing geotechnical monitoring equipment to track slope movement and groundwater levels, investigating drainage systems to inform future upgrades and carrying out progressive slope stabilisation at nearby sites.

READ ALSO Next stage of Lawrence Hargrave Drive works to begin

Federal Member for Cunningham Alison Byrnes said everyone who used the road understood how important it was as a connecting road for the northern Illawarra suburbs, both to Wollongong and Sydney.

“When the road is disconnected, it has a profound impact on our day-to-day lives,” she said.

“I know that local people also understand the complex challenges facing repairs along this stretch, and I want to thank everyone in the community for your patience while these works were underway.

“The concurrent spate of natural disaster events has severely impacted stability along this vulnerable stretch of road, and while I understand some further works along Lawrence Hargrave Drive are still awaiting repair, I am pleased to see this section completed.”

Free, trusted, local news, direct to your inbox

Keep up-to-date with what's happening in Wollongong and the Illawarra by signing up for our free daily newsletter, delivered direct to your inbox.
Loading
By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.

Start the conversation

Daily Digest

Want the best Illawarra news delivered daily? Every day we package the most popular Illawarra stories and send them straight to your inbox. Sign-up now for trusted local news that will never be behind a paywall.

By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.