24 June 2026

Amended design for Interchange's shared path bridge saves on vegetation loss

| By Jen White
Start the conversation
Road being built

Looking north at the intersection of the motorway and Mt Ousley Road in April. Work is due to start soon on land clearing for the shared overbridge. Photo: Transport for NSW.

People power has saved the amount of vegetation to be removed to make way for a shared bridge over the Mt Ousley Interchange.

Transport for NSW (TfNSW) has released an amended design for the shared 78 m bridge following feedback from the public which had raised concerns about the impact on nearby vegetation, among other issues.

“Construction of the shared path bridge will result in some environmental impacts. However, several impacts have been minimised as the design has been refined,” it says in its latest project update.

“The weaving boardwalk has been designed to avoid as many mature trees as possible and retain vegetation along Dumfries Avenue to provide a visual barrier between residents and the project, where possible.

“The refined design for the shared path bridge could result in the loss of up to 0.24 ha of additional native vegetation to what has already been removed for the project.

“To reduce the amount of vegetation removal, the team will be using the weaving boardwalk path as the construction access.

“We will be clearing a 6 m width along the boardwalk path to allow for a working area either side of the structure.

“We also require an area of 20 m by 25 m to build a piling pad for the bridge. We will continue working to retain vegetation, where possible.”

READ ALSO What a difference a year makes! The changing face of Mt Ousley Interchange

The community will be able to see the amended plans first-hand at a drop-in session on Thursday 25 June at Mt Ousley Public School. The project team will be on hand from 3 to 7 pm to answer any questions about the project. Entry to the school will be via Vereker Street, where parking will be available.

Work to clear the vegetation is due to start on Monday 29 June. Four nest boxes will be removed from the area before work starts and reinstated at a later time.

The revegetation strategy will include plantings that support habitat for small birds, including native species and in consultation with stakeholders including Wollongong City Council, Illawarra Landcare and the local Aboriginal community.

The shared 140 m long path will provide an accessible and safe active transport connection for people walking and cycling between the University of Wollongong and Wollongong TAFE precincts and suburbs to the north.

Map showing new overbridge

The amended design for the shared path bridge. Image: Transport for NSW.

The omission of the bridge from early plans for the interchange sparked controversy in 2024, when angry residents took TfNSW and local politicians to task after discovering it had been deleted without consultation.

Cycling groups and other stakeholders joined residents to demand the bridge be reinstated to provide pedestrians and cyclists a safe crossing over Mt Ousley Road.

The proposed concept design went out for public consultation last year.

TfNSW says modifications to the concept design also include:

  • Increasing the clearance between Mt Ousley Road and the bridge by 1 m to provide clearance for oversize, over mass trucks
  • Extending the shared user path on the northern side of Mt Ousley Road
  • Installing a raised pedestrian crossing and two additional traffic calming devices along Dumfries Avenue
  • Installing an accessible car space at the end of the old Mt Ousley Road cul-de-sac with direct access to the shared path.

The concrete deck will sit between the girders, not on top of them like the other bridges on the project. The girders are also the barriers and the connection point for the safety screens.

The bridge will have a 4 m wide deck, suitable for prams, mobility scooters, wheelchairs, bicycles and wheeled luggage.

It will cross Mt Ousley Road in one 54 m span, without a centre column which reduces visual clutter and maintains views.

READ ALSO Call for public feedback on plans for reinstated shared bridge over Mt Ousley Road

Two seated viewing areas will be provided along the shared path on both sides of the bridge to provide a rest stop and to enjoy the views west towards Mt Keira and east to the coast.

Each seat will be installed with enough space for a pram, mobility scooter or wheelchair to be parked next to the seat.

With just over 50 per cent of the project completed, the first major traffic change will occur mid to late this year on Mt Ousley Road and at the intersection of Mt Ousley Road and the M1 Princes Motorway.

Motorists will be moved onto a newly built section of Mt Ousley Road and a temporary section of road between Mt Ousley Road and the existing intersection at the motorway.

Mt Ousley Road between Gaynor Avenue and the motorway will remain one lane in each direction on the new alignment.

TfNSW says moving traffic onto this temporary section of road and new bridge allows work on the interchange and southbound heavy vehicle bypass lane to progress.

More information will be provided to the community ahead of the traffic changes.

A factsheet with more information including the key features of the refined bridge design is available on the project website, as well as the addendum review of environmental factors (AREF).

Free, trusted, local news, direct to your inbox

Keep up-to-date with what's happening in Wollongong and the Illawarra by signing up for our free daily newsletter, delivered direct to your inbox.
Loading
By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.

Start the conversation

Daily Digest

Want the best Illawarra news delivered daily? Every day we package the most popular Illawarra stories and send them straight to your inbox. Sign-up now for trusted local news that will never be behind a paywall.

By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.