Essential work on schedule to help protect coastline, improve accessibility to North Beach

| By Tania Brown
Start the conversation
Two people at beach

Wollongong Lord Mayor Tania Brown chats with senior project manager Sam Alger about progress on the North Beach seawall. Photo: Wollongong City Council.

Lord mayoral duties can take me all over our local government area on any given day.

I really love seeing and experiencing the breadth of council’s work for our community and enjoy the opportunity to hear directly from our residents about things that are important to them.

And one big project that has captured a lot of people’s attention is the second stage of works on the seawall and promenade at North Wollongong.

Which is why, on a picture-perfect winter’s day, I was pleased to take the opportunity to breathe in the sea air and visit the site for an update.

READ ALSO 'Ambitious' plan to shape housing supply, jobs, connections for Illawarra-Shoalhaven

Things are really moving forward on the multi-million dollar project that, once finished, will see the existing promenade and seawall extend all the way along the foreshore to between the North Wollongong Surf Club and North Beach Bathers Pavilion.

Right now, it is all very much a worksite. There are people wearing high-vis everywhere and heavy equipment and tools on-site and in use.

From the beach you can see six-metre-long metal screw pile sections lying on the sand and waiting for their moment to be pushed through the sand and down to the bedrock as footings for the seawall.

Once in, they’ll go to a depth of about 10 to 12 metres which is well beyond the few metres of sand that you can see on the beach.

X marks the spot of those piles in place with about 100 to go in total before the next stage of the works can start, which will see the start of the importing of fill around the piles, a new concrete base slab and then lifting in the new pre-cast concrete steps.

Two people in work site

The kiosk has been battered by harsh seaside conditions over the years and requires careful work to preserve its heritage and character. Photo: Wollongong City Council.

With the project making good progress, the team has been able to adjust the site fencing along the Blue Mile shared pathway, which remains open during the project.

By resequencing the works to allow for more on-site storage of materials, it has allowed for the compound to remain separate from the site and widened the pathway between the kiosk and pavilion buildings.

This is great news for people using this popular site as we know fencing was making it a little trickier and more congested, particularly on a sunny weekend.

As for the kiosk building, I was fascinated to hear how the team is overcoming the environmental challenges it’s uncovering within the building as essential repairs are carried out.

The brickwork here has really suffered the ravages of the harsh seaside conditions and, as more investigations have been made, it’s clear just how the mortar has disintegrated and the bricks are crumbling.

I take my hat off to the team for its patience as the crew works to preserve this heritage building as best it can – down to numbering each of the bricks as they’re removed so they can be cleaned and returned to exactly the same place – and finding ways of working that balance preservation and construction techniques to ensure the building is here for the next generations to enjoy.

READ ALSO 2026 Illawarra Business Awards finalists reflect 'strength, resilience and ambition'

The team has also pretty much wrapped up the works on the North Beach Bathers Pavilion. Here they repointed the external brickwork, carried out crack repairs and cleaned and replaced the damaged stringers (the brown concrete strip that runs around the building above its windows).

It is a real positive to see this project moving forward. This is an essential piece of work to help protect our coastline and improve accessibility to North Wollongong beach for everyone.

Once finished, people will be able to enjoy the Emma McKeon AM Promenade for many years to come. And right now, it remains on track to be completed by mid-2027.

You can read more about the project in our media release: Stage 2 seawall works underway.

We’re grateful to the NSW Government for its support of this project. The Stage 1 and Stage 2 seawall works were supported by technical and financial assistance from the NSW Government’s Coastal and Estuary Management Program, while the work to maintain and conserve the kiosk and pavilion is proudly funded by the NSW Government and council.

Free, trusted, local news, direct to your inbox

Keep up-to-date with what's happening in Wollongong and the Illawarra by signing up for our free daily newsletter, delivered direct to your inbox.
Loading
By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.

Start the conversation

Daily Digest

Want the best Illawarra news delivered daily? Every day we package the most popular Illawarra stories and send them straight to your inbox. Sign-up now for trusted local news that will never be behind a paywall.

By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.