It’s hoped specially built bat boxes will facilitate the departure of a colony preventing the reopening of West Dapto Road. Photo: Wollongong City Council.
A community Men’s Shed group has created makeshift habitats for microbats in the hope of encouraging the creatures to relocate from a culvert in West Dapto Road to the specialised boxes so that roadworks can continue along the vital stretch.
Volunteers from the Bulli-Woonona Men’s Shed have stepped in to help Wollongong Council address a major roadblock in the West Dapto Road construction project, after it was revealed that the discovery of a colony of threatened Southern Myotis bats would delay the road reopening to traffic.
Alongside a management plan being developed by the council, four specially designed microbat boxes have quickly been built to be installed near the culvert where the bats were found to help facilitate their departure from the site into an alternative habitat.
“We’ve all educated ourselves a bit and it’s great to be involved in things like this, it’s what the Men’s Shed’s about,” Bulli-Woonona Community Men’s Shed vice-president Peter Hurenkamp said.
“We’ve done some boxes before for bats, as well as for possums and various other things. For some boxes, [the brief’s] quite broad and non-specific, basically just a [specified] size. For the microbats here, they were very specific to work out an ideal design.
“We can do the job straight away and we love doing it. I virtually live in the Men’s Shed, I’m there five days a week, and it’s the sort of thing we do a lot of. It’s great to come out and have a look at them now that they’re installed and it’ll be interesting to see how it pans out. Hopefully it helps.”
Construction has continued to the east and west of the culvert; however, work has ceased in the immediate vicinity where the colony was found, delaying the anticipated mid-2026 reopening of West Dapto Road, which has already been closed to traffic for almost a year.
Wollongong Lord Mayor Tania Brown said: “It’s a complex problem to tackle, and we certainly appreciate the assistance of the Men’s Shed in getting the alternative habitat in place quickly.
“We understand people are keenly anticipating the reopening of the road due to the impact this is having on travel times.
“I can assure the community that construction has not ground to a halt, and we are working around the site to ensure the upgrade continues to progress.”
But despite community frustrations and the council’s efforts being implemented through the management plan, a clear timeline remains unknown, with the administration unable to force the departure of the threatened bats.
“We also need to act in an environmentally responsible way, which we are doing through our Microbat Management Plan,” Cr Brown said.
“It’s very difficult to predict the behaviour of wildlife, but we are committed to keeping our community updated as we get a clearer indication of anticipated timeframes.”
Updates on the project will be made available on the Wollongong Council website.