Threatened bats gone, West Dapto Road works due to finish by Christmas

| By Jen White
Start the conversation
roadworks

Work progresses on the West Dapto Road upgrade. Photo: Wollongong City Council.

West Dapto Road will reopen to traffic by Christmas, six months behind schedule mainly due to a colony of microbats.

The threatened bats, found in a stormwater culvert, stopped work in the area in May. A Microbat Management Plan was implemented in September and the bats have now moved on, allowing work to resume.

The heavily used road was closed on 29 July last year between Shone Avenue and Yard Street to construct stormwater drainage, a new shared path including pedestrian bridge, road pavements and the relocation of electrical and water services.

West Dapto Road is the only access road heading north for those living in Wongawilli.

At the time, Wollongong City Council said it expected the road to reopen in “mid-2026”.

Lord Mayor Tania Brown said then that council was aware the road closure would be a “temporary inconvenience”.

In an update in February, Cr Brown said the work was progressing well and the “road remains on track to reopen in July”.

READ ALSO The paddocks that will one day be home to Wongawilli Public School

However, the discovery of the microbats pushed the work out and because the threatened species could not be forcibly removed, council had to implement an “exclusion process” and wait for the bats to leave.

On Thursday (8 October) Cr Brown said construction had continued either side of the culvert site, with the permitted microbat exclusion process carried out through September.

Pavement works above the stormwater culvert can now progress under the supervision of an ecologist.

“With more than 86 per cent of works required to reopen the road now complete, the resumption of works at the culvert site is a major milestone for the project,” Cr Brown said.

“We understand the impact the road closure has had on residents and businesses, which is why our teams have continued progressing every available component of the project while the exclusion process was underway.

“Managing the presence of a threatened species within a construction site is a complex and carefully regulated process and we have worked closely with the relevant agencies to meet every requirement and keep the project moving forward.

“Restarting work at the culvert is a big step for the project and, with the progress we’ve been able to make on either side of the impacted site while the exclusion was underway, we’re now in a position to say the road will be reopened to traffic in time for Christmas.”

However, angry residents, who launched a petition in early September calling for rate relief and greater transparency on the situation at West Dapto Road, aren’t convinced.

Writing in response to council’s release on social media, one resident said the reopening was more likely “after the school holidays in January or February”.

Another wrote they “didn’t believe a word that Wollongong Council said”.

“We will continue to keep the community informed as works progress and look forward to seeing motorists, pedestrians and cyclists benefit from the upgraded road network,” Cr Brown said.

READ ALSO Bathla ordered to fix 'serious defects' at Kembla Grange development

The Lord Mayor gave an update on the work and said several key milestones for the project had been delivered while the microbat exclusion was underway.

“Pavement stabilisation works have progressed well this week following the placement of the lower and upper pavement layers, kerb and gutter installation at both the western and eastern ends of the road, and the shaping of road verges,” she said.

“Piling works for the pedestrian bridge have also been completed, with the bridge now fabricated and scheduled for installation later this month.

“While traffic will return to West Dapto Road once the critical works are completed, the community will continue to see construction activities around the site as crews work to finish elements which do not require a road closure and wrap up the current stage of this long-term project.”

Information on works completed to date is available on council’s West Dapto Road project page, which will continue to be updated fortnightly.

Community members can also sign up for regular project updates via council’s engagement page.

Free, trusted, local news, direct to your inbox

Keep up-to-date with what's happening in Wollongong and the Illawarra by signing up for our free daily newsletter, delivered direct to your inbox.
Loading
By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.

Start the conversation

Daily Digest

Want the best Illawarra news delivered daily? Every day we package the most popular Illawarra stories and send them straight to your inbox. Sign-up now for trusted local news that will never be behind a paywall.

By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.