6 September 2026

West Dapto microbat relocation lagging, road still months from reopening

| By Keeli Dyson
Start the conversation
bat and west dapto road

Microbats were discovered along West Dapto Road in June, delaying the project, which had already caused a year-long closure. Photo: Pavel German/DCCEEW (Supplied by Wollongong City Council).

West Dapto Road will remain closed to traffic for months, with the removal of the microbats delaying the process still not completed and residents offered no relief for their ongoing inconvenience.

Residents are fuming after a response from Wollongong City Council rejected the idea that compensation should be offered for the more than year-long closure of West Dapto Road and provided little confidence in the process of removing the microbats halting the completion of construction.

More than 1500 people signed a petition calling for clarity and transparency about the road, which was due to reopen midway through this year but hit a major delay after the discovery of a colony of threatened Southern Myotis microbats in a culvert.

A management plan was developed for the bats, and temporary habitat boxes were installed, but any further progress in their relocation has not been revealed.

In its response to residents, a council spokesperson said “relocation is to commence late August subject to four consecutive overnight temperatures exceeding 12 degrees Celsius”, but despite a run of warm weather at the end of last month and the start of September, the bats are still there.

READ ALSO Microbat discovery extends West Dapto Road closure, no timeline for reopening

Wongawilli resident and group representative Peta Dawson said she had since received clarity that the process was not so straightforward.

“I was told there are approximately 20 microbats in total and that council cannot relocate them. The bats have to relocate themselves,” she wrote in a Facebook post.

“So, when we’re told that all that’s required is four consecutive nights above 12 degrees celsius, that’s only part of the story, the bats actually have to choose to come out and relocate themselves.

“At every turn, it seems we are discovering new information that was never properly communicated to the ratepayers and residents directly affected by these works.”

A council spokesperson said: “With a pre-exclusion inspection by an ecologist now complete, council can begin active exclusion processes once overnight temperatures remain above 12 degrees for four consecutive nights.

“We are currently monitoring temperatures to determine when we can take additional measures to facilitate the safe departure of the colony.

“While the threatened species cannot be forcibly removed, the exclusion process involves sealing any gaps at night-time following microbats leaving to forage.

“The exclusion process will gradually continue until all gaps are sealed and the microbats have found alternative roost locations. This may include the four temporary habitat boxes installed by council in June to facilitate passive exclusion.”

Work has been continuing in other areas while the management of the bats is underway, but the connection will remain closed for months after they’re gone, with the spokesperson saying the target for opening two live lanes of West Dapto Road was “12-14 weeks post-relocation of microbats”.

Residents’ group member Kevin Green was tired of excuses for why it wasn’t completed when expected.

“They complain about the utilities, the services like the water and electricity, couldn’t coordinate those departments, which created all types of delays. If you’re taking on a major job of that size, would you not have all your ducks lined up in a row before you started the job?” Mr Green said.

“What they’re saying is all this delay and everything is because of the microbats, but if you go out there … you’d be surprised what they haven’t done, not what they have done.”

The council’s website states: “Council is also working through the feasibility of reopening one lane in morning and afternoon peaks. Some of the things we are considering include how this would impact our construction program, as well as safety, quality and cost.”

The original petition consisted of 11 requests, including more frequent updates and access to the management plan for the bats.

“A large amount of information regarding the project is published on council’s dedicated webpage in relation to remaining works, sensitive environmental matters related to the project, as well as percentage complete for key project elements,” the council response said.

“Due to the risks associated with managing threatened species, it would not be appropriate to release the management plan.”

The petition also called for an investigation and public report on options such as one-off rates rebates for directly affected households, a rates credit for a defined period, community grants or support measures for affected residents and local businesses, and other compensation or mitigation measures recognising the additional travel time and disruption caused by the prolonged closure.

“With a program of $604 million of capital works for the next four years across the City of Wollongong, it is simply unsustainable for the broader community to provide financial subsidy to community members impacted by public infrastructure works,” the council response said.

“Any rates rebates, credits or compensation provided to affected households could set a precedent and increase the cost of capital projects across the whole local government area.

“Regarding grant programs, council has multiple grants available, including Connecting Neighbours Grants, Sports Grants and Minor Donations.”

READ ALSO Threatened bats gone, West Dapto Road works due to finish by Christmas

The response caused outrage on the Community Action Group social media page, with some calling it ”pathetic” and ”a bloody joke”, while others say they are considering legal action or refusing to pay their rates.

Residents have since reached out to Shellharbour MP Anna Watson, who will be at the neighbourhood forum meeting on Wednesday (9 September) at Dapto Ribbonwood Centre, and is urging Lord Mayor Tania Brown to also attend to meet the residents face-to-face.

And the passionate residents are preparing to turn up in droves and have their voices heard.

“We can’t do much about the finish time on this now, but what we want to achieve is for them to recognise that they have, from the beginning, fed rubbish to the residents of West Dapto,” Mr Green said.

“We want somebody to be accountable, we want somebody to stand up and say, ‘We’ve done wrong’. Don’t just keep blaming microbats and other rubbish.”

Ms Dawson added: “This is a really important opportunity for our community.

“I strongly urge as many people as possible to attend. The more of us who are there, the stronger our message will be.”

Free, trusted, local news, direct to your inbox

Keep up-to-date with what's happening in Wollongong and the Illawarra by signing up for our free daily newsletter, delivered direct to your inbox.
Loading
By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.

Start the conversation

Daily Digest

Want the best Illawarra news delivered daily? Every day we package the most popular Illawarra stories and send them straight to your inbox. Sign-up now for trusted local news that will never be behind a paywall.

By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.