9 June 2026

What a difference a year makes! The changing face of Mt Ousley Interchange

| By Jen White
Start the conversation
Two views of roadworks

Progress on the Mt Ousley Interchange in a year. Photos: Transport for NSW.

It’s been well over a year since work started on the Mt Ousley Interchange and it’s getting harder all the time to remember how the M1 Princes Motorway once looked.

Drivers of the more than 50,000 vehicles that travel through the area daily can see the new roads and bridges taking shape each week.

A key structure is in place to connect Mt Ousley Road over the heavy vehicle bypass and girders have been placed for the new shared path over the southbound access road.

The project reached a major milestone in April, with the opening of the first heavy vehicle safety ramp at the base of the mountain.

READ ALSO Mt Ousley Interchange progress revealed with major milestones to come in 2026

The ramp provides a safe area for trucks and buses to stop if they experience engine problems or brake failure while descending Mt Ousley.

Transport for NSW is confident the project is on track to meet its expected completion date in 2028.

It’s when you compare photos of the site that you get the full picture – no pun intended – of just how much work has been done on the massive site.

The latest photos on the project’s website are from April, so we thought we’d compare a few to April 2025 to see how much has changed.

road works

Above (April 2025) and below (April 2026): Looking north over the intersection of the motorway and Mt Ousley Road. Photos: Transport for NSW.

road works
roadworks

Above (April 2025) and below (April 2026): The motorway looking south towards the pedestrian bridge at Northfields Avenue.

roadworks
roadworks

Above (April 2025) and below (April 2026): East towards Mt Ousley Road.

roadworks

What’s happening in June?

Major work will be carried out on Mt Ousley Road, between the motorway and Gaynor Avenue, necessitating a full weekend closure of the road from midnight Friday 19 June to 4 am on Monday 22 June, weather permitting.

Rain has forced the cancellation of the work a number of times already. Transport for NSW says if it’s cancelled again, the work will be rescheduled to the weekend starting Friday 26 June.

The work will include increasing the level of Mt Ousley Road and building new road pavement between Gaynor Avenue and the motorway, as well as building part of the new intersection at Mt Ousley Road and the motorway.

READ ALSO UPDATED: Mt Ousley Road weekend closure postponed for second time

For the latest information on the planned road closure, visit Live Traffic.

Workers have a long list of jobs for this month, including pruning, removing and mulching vegetation; installing and removing signage; installing and relocating temporary barriers; removing and installing guardrail; relocating and installing utilities and installing drainage along the motorway.

They will continue work on retaining walls and bridge structures including installing girders; the second heavy vehicle safety ramp and the noise wall next to Dumfries Avenue as well as landscape preparation work on Dumfries Avenue.

As well as the planned closure of Mt Ousley Road, motorists should be aware that lane closures and speed reductions will be in place at times on the motorway during June.

Free, trusted, local news, direct to your inbox

Keep up-to-date with what's happening in Wollongong and the Illawarra by signing up for our free daily newsletter, delivered direct to your inbox.
Loading
By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.

Start the conversation

Daily Digest

Want the best Illawarra news delivered daily? Every day we package the most popular Illawarra stories and send them straight to your inbox. Sign-up now for trusted local news that will never be behind a paywall.

By submitting your email address you are agreeing to Region Group's terms and conditions and privacy policy.